Florida

Florida Notice of Commencement: Who Files It and When You Need One

In Florida, the property owner is responsible for the notice of commencement. Under Chapter 713 of the Florida Statutes, the owner or the owner's authorized agent records it with the clerk of court in the county where the property sits. This has to happen before work begins. A copy is then posted at the job site: either a certified copy, or a notarized statement that the notice has been filed for recording, together with a copy of the notice. Your contractor will often prepare the form and may even take it to the clerk's office. Even so, the legal responsibility is yours, and in most cases you are the one who signs it.

Most permitted jobs need one, including new homes, additions, major remodels and roof replacements. Small jobs at or under a contract price set in the statute are exempt, and certain repairs are treated differently. The notice is more than paperwork. It is the document that starts Florida's lien process. If it is missing or handled badly, you can end up paying twice for the same work. The rest of this guide covers what the notice does, what goes on it, and how to check the current rules yourself.

What a Notice of Commencement Actually Does

Florida's construction lien law lets people who improve your property file a lien against it if they aren't paid. That includes subcontractors and material suppliers you never hired directly. If your general contractor collects your money and doesn't pay the roofing supplier, that supplier may have a lien claim against your house.

The notice of commencement is how the public learns that a project has started. It tells everyone on the job:

  • Who owns the property and what interest the owner holds
  • Who the contractor is
  • Who the lender is, if there is construction financing
  • Whether there is a payment bond
  • Who should receive legal notices about the project

Subcontractors and suppliers who don't have a contract with you use this information to send you a Notice to Owner. That notice is your warning that they are working on your project and expect to be paid. As Notices to Owner arrive, you build a working list of the parties who could file a lien. You can then make sure each of them is paid before you release money.

Without a recorded notice, that system breaks down. You lose the clear record of who is working on your home, and payments you make may not protect you the way you expect.

Who Files It: Owner, Contractor or Lender?

On most real projects, the responsibility and the actual work are split.

The owner

The statute puts the duty on the owner or the owner's authorized agent. The owner signs the notice under oath before a notary, so read it before you sign. If the property is owned by an LLC, a trust or more than one person, the right person has to sign. That means an authorized officer, a trustee, or each titleholder where required. Check with the clerk or your attorney if ownership is not simple.

The contractor

In practice, many licensed contractors fill out the form, have the owner sign it, and record it themselves or through a permit runner. That's normal and fine. But the contractor's convenience doesn't change the law. You should still:

  • Read every line before you sign
  • Confirm the contractor's name and license on the form match the Florida DBPR license search
  • Get a copy of the recorded notice showing the clerk's recording information

The lender

If you have a construction loan, your lender may need the notice recorded in a particular order relative to the mortgage. The lender may also handle the recording as part of closing. Ask your lender early how they want it done, so the paperwork doesn't hold up your first draw.

Owner-builders

If you are building as an owner-builder under the exemption in Chapter 489, nobody else is going to do this for you. You prepare the notice, sign it, record it and post it. Because you hire the trades directly, you are dealing with each of them yourself. You may also receive Notices to Owner from suppliers and sub-subcontractors working for the people you hired. Keep every contract and notice organized from day one.

When You Need One

The general rule is that a notice of commencement is required before work starts on an improvement to real property. Florida ties it to the permit process. The permit must carry a warning that failing to record a notice of commencement can result in paying twice for improvements to your property.

Here is how the timing usually works:

  1. The permit is applied for or issued. Ask your local building department when it wants a copy of the notice.
  2. The notice is recorded with the clerk of court in the county where the property is located. Don't record it too early. Under section 713.13, a notice is void if the work it describes doesn't start within 90 days after recording.
  3. A certified copy, or a notarized statement that the notice has been filed for recording along with a copy, is posted at the job site where workers and inspectors can see it.
  4. Work begins.

For jobs above the exemption limit, the statute also requires a certified copy of the recorded notice, or a notarized statement that it was filed for recording, to be filed with the building department before the first inspection. If you skip the notice, your schedule can stall right there.

Jobs that may not need one

Chapter 713 exempts small jobs at or under a set contract price. Section 713.135 also treats certain heating and air-conditioning repair or replacement jobs differently. Those limits are written into the statute and have been changed before, so don't rely on a number you heard from a neighbor or found on an old website. Check the current text of Florida Statutes Chapter 713, especially sections 713.02, 713.13 and 713.135. You can also call your county building department.

If you aren't sure whether your job is exempt, ask the building department before work starts. When in doubt, recording a notice is usually the safer choice.

What Goes on the Form

Section 713.13 lists the information a notice of commencement must contain and includes a standard form. Many county clerks and building departments provide a version of it. You'll generally see:

  • The property's legal description, street address and tax folio number if available. Use the legal description from your deed, not just the address.
  • A general description of the improvement, such as "reroof," "kitchen remodel" or "new single-family residence"
  • The owner's name and address and their interest in the property
  • The fee simple titleholder, if that's different from the person contracting for the work
  • The contractor's name and address
  • The surety and bond amount, if there is a payment bond
  • The lender's name and address, if any
  • A person in Florida the owner designates to receive notices, plus an optional additional person to receive copies of lienors' notices
  • The expiration date of the notice, if different from the default
  • The owner's signature, made under oath and notarized

Watch the expiration date

A notice of commencement doesn't last forever. Under section 713.13, it expires one year after recording unless the notice states a different date. If your project could run long, as new builds and big remodels often do, think about this before you sign. Payments you make after the notice expires are considered improper payments under the lien law. That is exactly the double-payment problem the notice is supposed to prevent. The form itself carries a warning about this.

If the project is going to run past the expiration date, talk to the clerk's office or an attorney about your options before it lapses.

After It's Recorded: Protecting Your Money

Recording the notice is only the first step. The protection comes from what you do with the information afterward.

Keep every Notice to Owner

Each Notice to Owner you receive identifies a party who could file a lien. Keep them in one file and match each one against the work being done.

Get lien waivers before or with each payment

Before you release a draw or payment, ask for lien waivers (releases) from the contractor and from every subcontractor and supplier who sent you a Notice to Owner. Section 713.20 includes statutory waiver forms for progress payments and final payment. Waivers should match the amount and the period being paid.

Get the final payment affidavit

When final payment comes due, Florida law requires the contractor to give the owner a contractor's final payment affidavit. It states either that everyone under the contract has been paid in full or which parties haven't been paid and how much they're owed. Don't make the final payment until you have it and have checked it against your Notices to Owner.

Closing out the notice

When the job is done and everyone has been paid, the owner can record a notice of termination under section 713.132. This ends the notice of commencement. The statute sets conditions for doing this, including making sure people who served a Notice to Owner have been paid or properly notified. Read that section or get professional advice before you file one.

Common Mistakes Homeowners Make

  • Signing a blank or half-filled form. Never sign a notice with empty fields for someone else to complete.
  • Wrong legal description. A mistake here can cause problems with the record. Copy it exactly from your deed.
  • Wrong owner listed. If title is held by more than one person or an entity, make sure the notice reflects that correctly.
  • Recording too early. If work doesn't start within 90 days of recording, the notice is void.
  • Letting it expire mid-project. Put the expiration date on your calendar.
  • Paying without waivers. The notice tells you who to protect against. Waivers are how you actually protect yourself.
  • Hiring an unlicensed contractor. A notice of commencement won't fix problems that come from hiring someone without the proper license. Verify the license before you sign anything.

Where to Confirm the Current Rules

Florida's lien law is detailed, and the legislature does amend it. The most reliable sources are:

  • Chapter 713, Florida Statutes, especially sections 713.13 (notice of commencement), 713.135 (permits and notices), 713.06 (notices from parties without a direct contract), 713.20 (waivers and releases) and 713.132 (notice of termination)
  • Your county clerk of court, for recording requirements, fees and accepted forms
  • Your county or city building department, for when they need a copy during permitting and inspections
  • A Florida construction or real estate attorney, for anything unusual about your ownership, financing or project

A notice of commencement brings in a lot of paperwork: Notices to Owner, waivers for every draw, and a final affidavit. Keeping all of it in one place with your budget and payment schedule makes it much easier to see who has been paid before you release the next check. If that would help, the Paper to Home build portal for homeowners keeps contracts, draws and lien waivers on one project page.

Your next step: Before you sign a notice of commencement, look up your contractor's name and license number in the DBPR license search. Then compare the legal description on the form, line by line, with the one on your deed.